A New Smokebox Door Seal For 6A
Re-Wheeling An NG/G16
NG/G16 129 Engine Unit Frames Near Completion
Another New Boiler For Puffing Billy!
Sustaining The Operation
NG/G16 129 Is Coming Together....Virtually!
Meanwhile...
First Pictures Of The New NG/G16 Boiler Construction!
Rebuilding Carbon
NG/G16 Workshop Progress
Testing continues on the NG/G16, with work currently focused on testing and proving of boiler fittings and pipework; injectors, pressure gauge and water gauges, blower, safety valves and whistle have all been tested.
The functionality of the ashpan and slides, rocking grate and dump grate has all been checked.
Once some final fettling of the safety valves has been completed, the boiler inspector will pay us a visit and sign the boiler operation off before we progress to the next stage of testing….
The post A New Whistle In The Hills! appeared first on Puffing Billy.
This article first appeared on puffingbilly.com.au
About this website
Railpage version 3.10.0.0037
All logos and trademarks in this site are property of their respective owner. The comments are property of their posters, all the rest is © 2003-2019 Interactive Omnimedia Pty Ltd.
You can syndicate our news using one of the RSS feeds.
Stats for nerds
Gen time: 1.0954s | RAM: 6.44kb