The Theemsweg route in the port of Rotterdam is now connected to the existing Harbour Line. On Monday morning 8 November 5 am, the first freight train ran on the four-kilometer-long track. According to the Port Authority, time savings, greater rail capacity and better accessibility are the advantages of the 300 million euro structure.
The six-day closure of the Harbour Line that was necessary for this has now come to an end. Rail freight traffic to and from the port of Rotterdam can be resumed, although it will take another week before all is back to normal. Train traffic will be built up to regular levels now, according to ProRail.
Replacement of old bridge
The Theemsweg route replaced the Caland Bridge, which opened for ships several times per day. The new structure consists of a viaduct and two bridges, so that rail freight is not impacted by barge. The projected benefit is an increase of rail capacity from 90 to 230 trains per day.
The Port of Rotterdam Authority, the national government and the European Union invested in the Theemsweg route, which cost a total of more than 300 million euros. The Port of Rotterdam Authority coordinated and realised the project in collaboration with ProRail and the Ministry of Infrastructure and Water Management.
The route
The Theemsweg route runs from Merseyweg, on a railway viaduct alongside Theemsweg, all the way up to Moezelweg via Neckarweg. The railway line passes two arched bridges (near the Thomassen Tunnel and the Rozenburg Lock) and links up again with the existing track where it meets the A15 motorway.
The project had a long run. Preparatory work started in 2016. A year later, in 2017, the cycle path was relocated. In 2018, the bridge was raised ten meters and part of the concrete windshields were removed and replaced in a different location. Sound-proof walls of 1.70 meters were also installed to dampen the noise of the trains racing by as much as possible.
This article first appeared on www.railfreight.com
About this website
Railpage version 3.10.0.0037
All logos and trademarks in this site are property of their respective owner. The comments are property of their posters, all the rest is © 2003-2022 Interactive Omnimedia Pty Ltd.
You can syndicate our news using one of the RSS feeds.
Stats for nerds
Gen time: 1.2434s | RAM: 6.43kb